Data Center Investors Underestimate Climate Risk, Report Says

By | November 16, 2026

The fallout of climate change may expose the world’s data centers to losses that investors aren’t currently pricing in, according to a report published on Oct. 13 by Jupiter Intelligence.

The privately-held risk analytics company estimates that annual losses from floods, wind and wildfires could be around $4.4 billion. It’s “simply not a priority” for investors, said Wahib Ghazni, the report’s author. Lenders financing data centers in emerging markets are at greater risk than those in developed ones, he added.

A study earlier this year of roughly 2,600 planned data centers worldwide indicated that more than 150 will be built on sites facing a high physical climate risk, with key hazards including coastal inundation, high heat and riverine flooding. A separate analysis by Schneider Electric Research Institute found that climate risk puts 38% of the value of the world’s data centers at risk, before adaptation measures are taken.

Most of the risk, or 61%, is to IT equipment, rather than buildings housing data centers, the Jupiter Intelligence report found, adding that such climate impacts are currently largely uninsured. The debt financing such infrastructure is typically short-term, whereas much of the increase in climate-related costs identified in the report will emerge over the longer term, it said.

The Jupiter Intelligence study, which modeled its analysis on more than 14,000 already operational data centers, highlighted risks to hubs in China, where insurance coverage is low and the risk of floods is high. China, including Hong Kong, represents 17% of the value of data centers in the world, but has 49% of the potential climate loss. North America, by contrast, has 44% of the value and 17% of the potential loss.

“The huge problem in China is pure geography,” according to Ghazni. “Many of the data center hubs are in three low-lying deltas and flood plains, exposed to monsoon rain and typhoons.”

What BloombergNEF Says:

Keeping data centers cool is becoming more expensive. BloombergNEF estimates a facility in Dubai requires about 30% more cooling-system capital expenditure than an equivalent one in Norway because higher temperatures reduce cooling-system performance, forcing developers to install more cooling capacity.

Photo: Photographer: Kyle Grillot/Bloomberg

Topics Climate Change

Was this article valuable?