Alabama Beach Repairs Could Take a Year, Could Cost $13 Million

September 26, 2008

Separate emails using a comma.

Damage estimates indicate hurricanes Gustav and Ike washed about a million cubic yards of sand apiece from Alabama’s Baldwin County beaches, and repairs could cost more than $13 million.

Gulf Shores Public Works Director Mark Acreman said it will take up to a year to replace sand and restore the berm that protects homes and condominiums.

Acreman said obtaining permits, conducting surveys and finding the right kind of sand could take six months, with construction lasting another half year.

He said Hurricane Gustav shaved a few feet of height from the beach in Gulf Shores, while Ike reached the lower beaches, breaching the berm at its base.

Coastal Resources Director Phillip West says Orange Beach lost about 500,000 cubic yards of sand and a mile of snow fencing between the storms.
___

Information from: Press-Register,

http://www.al.com/mobileregister

Separate emails using a comma.
Subscribe Like this article?
Subscribe to our free email newsletter.

Latest Comments

  • September 27, 2008 at 12:13 pm
    wudchuck says:
    so why rebuild a beach? why not leave what mother nature left? it's going to cost the taxpayers that much more money that could be used elsewhere. the only protection i wou... read more
See all comments

Add a Comment

Your email address will not be published. Required fields are marked *

*

More News
More News Features