The contractors who built Bertha the tunnel machine in Washington two years ago have filed a lawsuit seeking $11 million in extra pay.
The contractors contend that their efforts working with tough soil conditions cost more than originally anticipated.
Malcom Drilling Co., which created the 120-foot deep access vault, filed the lawsuit against Seattle Tunnel Partners earlier this year.
Seattle Tunnel Partners are the primary contractors for the future State Route 99 Alaskan Way Viaduct. They hired Malcolm to repair the massive machine after it stalled due to overheating.
According to the lawsuit, Malcolm contractors had to fend off sloppy soils and groundwater much than expected to access the damaged machine.
The Seattle tunnel was the preferred choice to replace the viaduct when it was damaged in a 2001 earthquake. But the tunnel boring machine broke down in late 2013, leading to a more than two-year delay while it was fixed.
Topics Lawsuits Washington Contractors
Was this article valuable?
Here are more articles you may enjoy.

Florida OIR Approves Four More HO Rate Cuts as Citizens Keeps Shrinking
A-Cap Insurers File Suit Against SCDOI Director; AM Best Downgrades Group
Hellman & Friedman Explores Sale of Applied Systems at Up to $10B, Sources Say
Independent Agencies Total About 37,000 in 2026, a Decrease From 2024 