The New York Thruway Authority has filed a lawsuit against multiple companies over the failure of four wind turbines.
The authority says in its lawsuit filed Thursday the turbines located along the Thruway in Erie and Chautauqua counties went offline between October 2017 and January 2018.
The turbines were installed in 2013 and 2014 as part of a renewable energy initiative.
The lawsuit is alleging negligence, professional malpractice, breach of warranty and breach of contract. WIVB-TV reports the authority is seeking $8.1 million plus interest, costs and collection fees.
One of the agencies named in the lawsuit, Kandey Company Inc., says it has not been served. Still, Kandey says it is confident it did nothing wrong and will be vindicated in court.
Was this article valuable?
Here are more articles you may enjoy.
Married Insurance Brokers Indicted for Allegedly Running $750K Fraud Scheme
India’s GIFT City Attracts Lloyd’s and Other Global Reinsurers, Sources Say
AIG, Chubb Can’t Use ‘Bump-Up’ Provision in D&O Policy to Avoid Coverage
Howden-Driven Talent War Has Cost Brown & Brown $23M in Revenue, CEO Says 