The leaky dam at Hyatt Lake in Oregon is being shored up this summer as part of a $3.7 million seismic retrofit.
The Mail Tribune reported the project will bring the dam east of Ashland into safety compliance after a seepage issue was discovered during a 2009 inspection.
Greg Garnett of the federal Bureau of Reclamation says engineers are nearly finished with designs. Work is expected to start in mid-May and run into mid-November.
Because of the project, Hyatt Lake will be kept no higher than four feet from full pool this summer,
That’s not expected to impact the Talent Irrigation District’s ability to store and deliver irrigation water this year. It also won’t change the Oregon Department of Fish and Wildlife’s trout-stocking plans.
ODFW plans to stock 10,200 legal-sized trout there this spring and 39,000 larger fingerlings in October.
Topics Catastrophe Natural Disasters Oregon
Was this article valuable?
Here are more articles you may enjoy.
What Analysts Are Saying About the 2026 P/C Insurance Market
Insurance Broker Stocks Sink as AI App Sparks Disruption Fears
AIG’s Zaffino: Outcomes From AI Use Went From ‘Aspirational’ to ‘Beyond Expectations’
A 10-Year Wait for Autonomous Vehicles to Impact Insurers, Says Fitch 