Hartford’s mayor says work is set to resume on the city’s problem-plagued minor league baseball stadium, months after it was scheduled to open.
Mayor Luke Bronin says the surety bonding company, Arch Insurance, has hired an architectural firm to complete some of the work left undone by developers DoNo LLC and Centerplan Construction.
Bronin fired the developers following a series of missed deadlines on the $63 million park, which was originally scheduled to open in April.
Under its agreement with Arch, the city will be paying $245,000 for work previously done by Pendulum, the Kansas City-based architects, and the insurer will pay for the new work.
The Double-A Yard Goats, which have played this season on the road, could leave the city if the ballpark is not finished in six months.
Topics Carriers
Was this article valuable?
Here are more articles you may enjoy.
Marsh Awarded Injunction Against Former Employees Now With Howden US
Florida OIR Slams Committee-Approved Clearinghouse Bill Changes as ‘Illusory’
Florida Appeals Court Pulls the Plug on Physician Dispensing in Workers’ Comp
Cuts to Funding Mean Risks Will Pivot in Human Services Market 