The University of Akron in Ohio is suing several companies over the condition of railings in the school’s stadium, saying shoddy construction and design led to $1 million in needed repairs.
The university lawsuit included photographs that show railings at Infocision Stadium missing chunks of concrete and with big cracks. The school blames problems at the decade-old stadium on “poor design, failed overnight and construction deficiencies.”
University spokesman Wayne Hill tells the Akron Beacon Journal that efforts to resolve the matter without filing a lawsuit were unsuccessful.
The stadium built in 2009 cost $71 million and holds about 30,000 people.
Welty Building Co., the construction manager, says a contractor improperly installed railings and Welty has worked continuously with the university over several years to help fix the problem.
Topics Lawsuits Education Universities
Was this article valuable?
Here are more articles you may enjoy.
Florida Supreme Court Posts New Rule on AI Hallucinations in Court Filings
Sentry to Sponsor PGA Tournament at Torrey Pines
Shipper Escapes $41.9M Award for Man Paralyzed When Lights Fell From Pallet on Him
DeSantis Plan to Cut Florida Property Taxes Heads to Ballot—With Schools Removed 